RTHF Machine Foundation, Chimney Foundation & Flue Duct

Area: 33000 sq. ft.
RTHF – Dia.32m, Depth 4m
Chimney Foundation & Flue Duct – Length 33m x Width 16m x Depth 6.5m
Type: RCC
Cost: 1.5 CroreCompletion period: 6 months

PQF Mill & Cross Transfer Foundation

Area: 45000 sq. ft.
Foundation Length 105m x Width 28m x Depth 8m
Type: RCC
Cost: 6 Crore
Completion period: 6 months

Cooling Bed

Area: 25000 sq. ft.
Size of the foundation 52m x 30m, Depth 3m
Type: RCC
Cost: 1.5 Crore
Completion period: 3 months

Demolition of RCC Building

Area: 27000 sq. ft.
Demolition of old RCC multi-stored building
Type: RCC
Cost: 24 Lacs
Completion period: 1 month

PQF Shed

Area: 98490 sq. ft.

Shed area 300 x 30.5m. Column foundation, trimix flooring, electrical trenches, small machine foundation
Type: RCC
Cost: 158 Lacs
Completion period: 8 months

Foundation of Lauses Straighter Rotary Saw & Collecting Bins

Area: 21700 sq. ft.
Type: RCC
Cost: 39 Lacs
Completion period: 2 months

Other small foundations

Shell Manipulator foundation
Hollow Blome Manipulator foundation
Conveyer foundation
Extracting Mill foundation
Short Blasting foundation
Cooling Tower foundation
Layer Formation & Circular Saw foundation
Contact Persons
Mr. Desai (Project head)
Mr. Dineshsingh Rajput (Civil head)
Mr. Arvind Rastogi (Head – Materials)
Mr. Jagdish Deshmukh (RCC Consultant)

Jindal Saw Ltd., Sinnar, Nashik